Shell Green Mersey valley processing centre extension

Jan. 16, 2012
0.511.522.533.544.55 (0 votes)

An extension to an existing sludge incineration and treatment plant

The Client
United Utilities (UU) are the 2nd largest water company in England /Wales. They are responsible for an area in the north west of the UK, which includes major cities such as Manchester and Liverpool.

The Solution

Background
The Mersey Valley Processing Centre (Shell Green) Extension is the current'Flag Ship' project for United Utilities. The project will improve the sludge incineration capability at Shell Green and to maximise the energy recovered from the heat generated increasing the efficiency of the plant. The contract is a Joint Venture with Veolia Water Solutions & Technologies and Costain called S3JV.

Services Provided

  • Design management
  • Construction management
  • Risk management
  • Fixed price, fast-track contract
  • 3D interactive modelling
  • Integration of all detailed design, procurement, construction, testing and commissioning of civil, mechanical and electrical works

The Process

Expansion of existing facility for drying and incineration of sewage sludge, involving all design, procurement, civil and M&E works for:

  • Modification to the sludge pumping station and reception tanks
  • Phased removal of existing dewatering equipment and replacement with 8 centrifuges complete with supporting steelwork, associated pumps, pipework, instrumentation, control panels and temporary dewatering facility
  • Construction of new centrate treatment facilities for solids and nitrogen removal and a new conveyor system to transport centrifuge sludge cake
  • Provision of additional fluidised bed incinerator with associated systems, & provision of additional stream of gas cleaning with partial replacement of existing. Modify/Replace/Augment ash silo and transport systems
  • Substantial modification of existing condensing turbine generator to maximise electricity generation
  • Modification of the existing and the construction of new Scrubber Effluent Treatment Plant
  • Modify existing and provide new: cooling, potable, process and fire main water systems; gas supply; odour control system; electrical infrastructure; communications and control equipment; standby generator

 

RELATED KEYWORDS

MOST POPULAR RELATED SEARCHES


Post a new comment

Post your comment

View comments

No comments were found for Shell Green Mersey valley processing centre extension. Be the first to comment!



Contact Us | Advertise | FAQs | Add Your Company | About Us | Terms | Privacy Policy | Company Sitemap | Category Sitemap | Professional Profiles Sitemap

Environmental Expert LinkedIn LinkedIn | Environmental Expert Twitter Twitter | Environmental Expert Facebook Facebook | RSS Feeds RSS | Environmental Expert Blog Blog

©1999-2012 Environmental Expert S.L.
Air & ClimateEnergy & RenewablesEnvironmental ManagementHealth & SafetyMonitoring & TestingSoil & GroundwaterWaste & RecyclingWater & Wastewater