Assembly of Methan-Digesters in Benesov - Case Study

0

Courtesy of GLS Tanks International GmbH

After only a short erection time of 3 month the heart of the plant, the two digester are completed. With a diameter of 9 m and a height of 18 m and their appearance is an indication for the total size of the plant.

The erection is affected as all projects of GLS Tanks International GmbH by international cooperation. Our erection crew installed both digesters together with Czech helpers in record time. This was at the time a logistical and organisational challenge for all of them. Despite very bad weather conditions, the two digesters were assembled as originally scheduled. In a final step we finished the last part of our scope of delivery; the insulation. At the beginning of July we handed over the completed tanks.