Project Name: Methodist Le Bonheur Germantown Hospital & Fire Department Test

Products: Grasspave2

Applications:  Grass fire lane

City: Germantown

State/Province: Tennessee

Install Date:  April 2008

Client: Methodist Le Bonheur Germantown Hospital

Install Size: 1800 sq meters (19,400 sq ft)

Address: 7691 Poplar Ave, Germantown, TN 38138

Designer:  NA

Contractor: Pro Green Landscapes

Directions: 7691 Poplar Ave, Germantown, TN 38138

Summary: The Germantown Fire Department required onsite testing for the Hospital fire lane installation.   Invisible Structures recommends testing with grass grown on the system (with two weeks of rooting), however even without grass, this installation passed with flying colors.

Even with the fully extended ladder, the outriggers are no match for the impressive 15,940 psi compressive strength of Grasspave2.