Remediation Products Incorporated (RPI)

Case study – PCE contamination pilot study


Courtesy of Courtesy of Remediation Products Incorporated (RPI)

Site: Dry Cleaner (North Carolina)
Contaminant: PCE
Soil Type: Saprolite
Injection Cost: $35,000 (material & labor)
Pilot Treatment Area: approximately 1460 sq. ft.
Thickness: 11 to 41 feet bgs
Injections: 16 per borehole
Groundwater: varies from 13 to 15 feet bgs
Site Status: Preparing to proceed with full site treatment – October 2007