Christ the King School - Case Study

0

Courtesy of Modulek

Project: Christ the King School

Client: Bournemouth Borough Council

Completed: August 2015

Floor area: 668m2

Duration: 6 weeks

Location: Bournemouth, Dorset

Value: £1,200,000

Turnkey service elements completed:

  • Design
  • Groundworks
  • Off-site Manufacture
  • Installation
  • Internal Fit Out
  • Service Connections

‘Just want to say many thanks for all you hard work and completing once again a stunning building’

The project was a fast track operation enabling the client to have vital primary teaching space up and running for the new September term, to meet the demand for extra places in the local catchment area.

Modulek were able to carry out the project in the six week summer holiday period ensuring the school experienced the minimum of disruption, on what is a logistically challenging site with the confined space to work within.

The design of the building had to blend in with the surrounding traditionally constructed buildings so that was of a permanent appearance on a par with the adjacent structures on-site.