Courtesy of Agru Ireland Ltd. T/A Lining Tech

Lining Technology have successfully been awarded the contract for the Derryclure Landfill Phase 2 Capping project by Offaly County Council. The contract is for the supply and installation of a 4 layered geosynthetic capping system over the phase 2 capping area (38,000m2). Other works to be completed as part of the contract include the installation of gas extraction and drainage pipework and associated civils works. The start date for the contract is Tuesday 10th April 2012 and works will take approximately 4-5 months to complete.