In early 2002, it became clear that maintenance on the grit removal system at the Sacramento Regional Wastewater Treatment Plant (SRWTP) was required. Moving 100+ million gallons per day (MGD) of grit was quickly wearing out the original steel pipes, and replacement was needed. After testing several piping systems, the SRWTP decided to replace a section of steel pipe with DuraplusTM Industrial ABS to test its durability and reliability.After more than five years of service, the Duraplus Industrial ABS test spool and 90° elbows showed no signs of wear. The SRWTP engineering and operations group decided to begin replacing all of the steel pipe on the grit removal system with Duraplus Industrial ABS.

Customer comments

No comments were found for Duraplus replaces steel pipe at the Sacramento Regional Wastewater Treatment Plant Case Study. Be the first to comment!