Perkins Engines Company Limited

Edina Secures Large Data Centre Rental


Courtesy of Courtesy of Perkins Engines Company Limited

In November 2008 Edina secured an order from Dornan Engineering to supply critical standby generation plant and fluid chillers for phase 1 of a new datacentre in Stockholm Sweden. Phase 1 would involve the complete fit out of a 400m2 data hall 1500 watts /m2. The data centre was scheduled to open in February and in order to facilitate the rapid build schedule Edina’s equipment needed to be on site by 5th January 2009. Although phase 1 would only remain in place until phase 2 was completed the entire installation needed to meet the same exacting standards as the permanent installation and would be operational for up to 12 months.

Customer comments

No comments were found for Edina Secures Large Data Centre Rental. Be the first to comment!