Field Project : Central Nevada - Case Study

0

Project Location: Central Nevada
Volume of soil: 1000 yd3
Contamination type(s): JP-8
Average level of contamination: 15 - 18,000 PPM
Results from confirmation testing: Non-detect for JP-8

Location: Central Nevada
Treatment: Surfactant w/catalyst oxidizer
Volume of soil: 1000 yd3
Contamination type(s): JP-8
Average level of contamination: 15- 18,000 PPM
Peak levels of contamination: 18,000 PPM
Elapsed time for project: 5 Days
Elapsed time after completion prior to collecting confirmation samples: 21 Days
Number of confirmation samples collected: 20
Results from confirmation testing: < 1ppm Non-detect for JP-8.