EarthWorks Environmental Inc. | CleanSoil Technologies, Inc.

Field Project : Eastern Wyoming - Case Study

0

Project Location: Eastern Wyoming
Volume of soil: 2750 yd3
Contamination type(s): Gasoline and diesel fuel
Average level of contamination: 3800 PPM diesel; 60 PPM gasoline
Results from confirmation testing: Non-detect for diesel fuel, gasoline and BTEX (sensitivity at parts-per-million) for all samples.

Location: Eastern Wyoming
Treatment: Bio Enhanced Surfactant
Volume of soil: 2750 yd3
Contamination type(s): Gasoline and diesel fuel
Average level of contamination: 3800 PPM diesel; 60 PPM gasoline
Peak levels of contamination: Unknown, but some sections saturated with contaminant liquid/free product gasoline
Elapsed time for project: Nineteen days (majority of soil was pre-screened to remove an extensive concentration of debris, including large chunks of concrete and asphalt)
Elapsed time after completion prior to collecting confirmation samples: Twenty-three days
Number of confirmation samples collected: 60 samples collected, 30 for testing for diesel and 30 for testing for gasoline and BTEX
Results from confirmation testing:Sensitivity: 10ppm

Customer comments

No comments were found for Field Project : Eastern Wyoming - Case Study. Be the first to comment!