Courtesy of Modulek

Project: Rugby Changing Room Facilities

Client: Bournemouth Borough Council

Completed: April 2012

Floor area: 208m2

Duration: 3 weeks

Value: £335,000

Turnkey service elements completed:

  • Design
  • Base preparation
  • Delivery and installation
  • Access footpaths
  • Service connections to include; electric, water, gas and drainage
  • Demolition of original existing building

‘The quality and finish of the building exceeded our expectations. Modulek met the contract requirements throughout, and the building was delivered on time and within budget. The single thing that impressed most was the professional approach during the whole process, from the feasibility stage to delivery, to after installation dealing with any problems efficiently.’