Client: Bournemouth Borough Council

Completed: August 2014

Number of Modules: 78

Duration: 7 months

Value: £2.6m

Turnkey service elements completed:

  • Design
  • Groundworks
  • Manufacture
  • Delivery and installation
  • Service connections
  • Access facilities
  • Playgrounds
  • Car park

“The building that was supplied and erected by Modulek was going to be a short term measure for classroom space, the building and your after sales is so good we are at this moment seeking planning to keep the building on a permanent basis, the staff using the class rooms do not want to go back into their old rooms which I might point out are brand new classrooms”

Modulek completed a bespoke two-storey modular school building for the Jewell Academy School in Bournemouth. The new extension building provides the school with an additional 14 classrooms, a hall suitable for PE and drama, several group rooms, a library and administration area.

The new building is twice the size of the existing school buildings, enabling the school to grow.

Designed and finished to a very high standard, externally the building is a mixture of render brickwork and timber cladding giving the building all the appearance of a traditionally constructed extension.

Internally the finishes defy the modular logic with fully plastered walls, suspended ceiling, and cement board flooring ensuring the construction provides all the feel and appearance of a traditional building. External works included playgrounds, MUGA courts and a staff car park.

Customer comments

No comments were found for Jewell Academy - Case Study. Be the first to comment!