JCB Uttoxter - Case Study
CLIENT: JCB RECLAMATION STRATEGY: Integrated E-Clay Stabilisation, E-Clay Permeable Reactive Barrier, asbestos amanagement and material management. CONTAMINATION: Total Petroleum Hydrocarbon, Polycyclic Aromtaic Hydocarbon and asbestos END USE: Residential Site Background & History The former JCB Heavy Products Manufacturing Site is located at the southern end of Uttoxeter town ...
-
Asbestos contaminated soil removal - Glasgow
Asbestos Contaminated Soil Remediation Client: Hawkshead Properties Ltd Challenge: Removal of asbestos contaminated demolition material adjacent to residential housing and canal. Monitor air borne dust particulates and swab cleaned surfaces to validate target levels. Backfill excavations and make safes vertical drops. Applied technology: Excavation and removal of material to a licensed ...