Agru Ireland Ltd. T/A Lining Tech

KTK landfill capping - geosynthetic lining


Courtesy of Courtesy of Agru Ireland Ltd. T/A Lining Tech

Landfill capping works are currently ongoing at KTK Landfill, Kilcullen, Co. Kildare to complete the final capping works at the facility. The capping area of the project is approximately 93,000m2 with Lining Technology providing lining crews and an excavator for the supply and installation of both smooth and double textured LLDPE liner. Works also involved sealing around existing gas wells and extrusion welding of capping liner to the existing cell liner. Lining Technology have worked closely with the main contractor to coordinate and program the works. Works are anticipated to be completed in the summer of 2012.

Customer comments

No comments were found for KTK landfill capping - geosynthetic lining. Be the first to comment!