Learning curve proving steep for the Indian CSP industry

- By:

Courtesy of Courtesy of FCBI Energy

Phase 1 of the National Solar Mission aimed to provide India with a learning curve for its first steps into CSP, with recent developments suggesting that there are many lessons to take into the next phase.

In a recent interview Tarun Kapoor, Joint Secretary at the Ministry of New and Renewable Energy (MNRE), attributed delays in CSP project development to problems in the supply of critical materials and dust-clouds affecting solar radiation.

From a supply chain perspective, the key issue for CSP developers has been securing the heat transfer fluids from overseas – but this is not a new issue.  In July 2012, Mr. Kapoor told CSP Today that “some of [the Phase I developers] have asked for extension of time mainly because of delay in availability of heat transfer fluid.” 

Similarly, doubts have been cast over the accuracy of solar irradiation measurement on offer in India for a number of years. In response to this, the Centre for Wind Energy Technology (C-WET), an autonomous research and development institution under the MNRE, has initiated a major project on Solar Radiation Resource Assessment (SRRA) across the nation to assess and quantify the solar radiation availability along with weather parameters.

Despite the negatives, experts have pointed out that Phase 1 of the National Solar Mission was specifically designed by the MNRE to provide industry lessons when moving forward. Indeed, the official mission document stated that “The ambitious target for 2022 of 20,000 MW or more, will be dependent on the ‘learning’ of the first two phases, which if successful, could lead to conditions of grid-competitive solar power. The transition could be appropriately up scaled, based on availability of international finance and technology.”

At CSP Today India 2013 (12-13 March, New Delhi) developers, Government officials and industry leaders will be assessing the lessons of Phase 1, addressing themes such as finance, technology comparison and cost reduction.  Experts from the MNRE, C-Wet, Abengoa India, Godawari Green Energy, Cargo Power, the NVVN, KVK Energy Ventures and more will be showing attendees how to prove the ROI of their CSP business to win more funding & market share in India.

To find out more, visit the website:


or contact Matt Carr by e-mail matt@csptoday.com

Customer comments

  1. By Grace Bell on

    Vanguards Power (VP) is a leader in design, development and manufacture of 3rd Generation Power Optimisation Systems. VP Systems use state-of-the-art computer control to regulate and stabilise all incoming voltage into any building or site. All VP Single and 3 Phase Systems have our unique Dynamic Digital Voltage Control (DDVC) system. Output Voltage settings can be changed by the User at any time without site power interruption - which further increases energy savings, more than any other Power or Voltage Optimisation System in the World. VP range of single and 3 Phase Power Optimisation Systems are called: PropSava and LiteSava. Where Sites experience main voltage delivery over 220V phase voltage (380V line voltage) electrical equipment is overpowered; power is wasted and all electrical equipment suffers premature failure with reduced life expectancy. Http://www.vanguardspower.com