Royal Imtech N.V

Morden Underground Station


Courtesy of Courtesy of Royal Imtech N.V

Imtech was commissioned to undertake a Station Modernisation and Enhancement Project at Morden Station which comprised of the provision of new electrical and mechanical services as well as modification to the existing. As Morden is the last station on the Southern end of the Northern Line, work was restricted by very short engineering hours (typically 2 1/2 hours work per shift). All switchrooms were upgraded and new multi-compartment cable containment provided throughout the station. New lighting was integrated with the cable management system in the Ticket Hall. Additionally mechanical services to staff areas were installed and commissioned.