Agru Ireland Ltd. T/A Lining Tech

Orana WTS emergency pond - case study

0

Courtesy of Agru Ireland Ltd. T/A Lining Tech

Lining Tech have successfully completed subcontract geosynthetic lining works for Ostwald Bros on an Origin Energy APLNG emergency Pond in Orana, Queensland. The project included:

  • Installation of 36,000m2 of a 1.5mm HDPE geomembrane liner
  • Installation of HDPE level indicators to pond
  • Fabrication and installation of HDPE access ladders
  • Fabrication of HDPE sand tubes to ballast liner prior to commissioning
  • Compliance with work safe and cut safe policies

Installation crew consisted of:

  • 1 project manager
  • 1 supervisor
  • 3 Installation welding technicians
  • 3 labourers

Works were completed on time in 21 days