Pearl of Qatar Phase 1 - case study

0

Courtesy of Envac AB

The Pearl, Qatar is Qatar first free hold real estate development built on reclaimed land and sits on the shores of the Persian Gulf. The mixed use development under construction is designed to accommodate approximately 13,150 tenements or a resident population of 42,000 personnel and additionally about 300,000 people are expected to visit annually.

The entire development is spread across various zones which are classified based on the types of use and residential layouts. In order to satisfy the demand of dwellings and provide the associated facilities, the project is designed to have residential apartments, hotels, villas and theme based residential zones, retail shops, restaurants, large service areas, public amenities, and car parking space. In addition plans are afoot to accommodate a water based theme park,

The development consists of 13,150 apartments, 42,000 residents and expects over 300,000 annual visitors. Commercial area spreads across 119,000 Sqm a 900 room hotel and over 309,000 sqm of retail amenities.

The system covers towers with chutes, groups of independent villas are provided with outdoor inlets. The retail areas along the waterfront promenade are also located with inlets which cater to the retail and the marinas.

This contract also covers Operating and Maintenance for a period of 7 years and handles day to day operations, waste haulage, spares and consumables.

Owners
United Development Corporation

Consultants
Dar-al-Handasah, Shair & Partners

Scope of Work
Supply and commission main pipe net
Supply, install, commission collection station equipment
Build & construct collection station building
Supply, install & commission all feeder connections in plots
Operation, service, haulage of waste system for 8 years

Estimated waste/day
135 Tonnes

Dwellings
13,150 Nos

Hotel Rooms
895 Rooms

Commercial Offices
118,425 Sqm

Retail and Amenities
309,910 Sqm

Total Area of Development
4,000,000 Sqm

Collection Station
4 Nos Avg 30 - 35 tonnes / day

Length of pipe: Main Net
25 Kms

Length of pipe: Plot Connections
30 Kms

No of Plot Connections
In-door 120 Nos, Out-door 100 Nos.

Contract Period
Main Net Jan 2007 – May 2009
Plots May 2007 – June 2014

Operations
8 Years, haulage included

Current Status
Collections Stations Completed and Commissioned
Waste Collections – Phase 1 / 2 under operation - Phase 3 / 4 - Commissioned