Pulsed Hydraulics, Inc.

Tiffin, Ohio Installations - Case Study

0

Courtesy of Pulsed Hydraulics, Inc.

Mix three 25’ x 16’ x 18’ anoxic basins.

SPECIAL REQUIREMENTS:
TSS readings cannot exceed 10% variance from test stations located V from the top and V from the bottom. D.O. must not exceed .5 mg/L.

PHI SOLUTION:
Provide two bubble forming plates in each basin located in the tank pursuant to the CFD model and provide one 3-valve mixer controlled by an Allen-Bradley PLC. PHI also supplied a 10 hp rotary screw compressor with enough power to mix all three basins.

RESULTS:
PHI took 12 readings in each basin with customer's engineer. Highest D.O. measurement in all three basins was .05 mg/L and the highest TSS variance was 2%.