WES Limited

Water Utilities - Potable Water Treatment - Case Study

0

Courtesy of WES Limited

  • Project Title - Hall Water Treatment Works
  • Client - GTM JV / Anglian Water
  • Project Value - £350K
  • Chemical - Hydrogen Peroxide 50%
  • Duration - 18 months

Our Services

Potable Water Treatment
Design, build and site install a hydrogen peroxide dosing system c/w with control system.

Details

Water treatment
Anglian Water commissioned a new water treatment plant, opened in 2014, treating up to 20 million litres per day. The plant combines micro-filtration, GAC filtration and ultra-violet treatment to treat river water to drinking water standards.

Advanced oxidation can be achieved with a combination of Hydrogen Peroxide dosing and ultra violet radiation. WES Ltd designed and installed the entire Hydrogen Peroxide installation including a 25 m³ bulk storage facility, dosing pumps and controls to dose chemical at the remote Points of Application.  The new installation complies with the CEFIC standard.

Customer comments

No comments were found for Water Utilities - Potable Water Treatment - Case Study. Be the first to comment!