We`ll never rod another heat exchanger again case study

0

Courtesy of Apex Engineering Products Corporation

A California gas plant was experiencing heavy scale deposits in its entire plant cooling system.

RYDLYME approach

  • 6,600 gallons of RYDLYME was recommended for the 33,000-gallon system.
  • Due to the large volume of water and low concentration of RYDLYME (20%), the system was divided into three isolated loops with each loop circulated with the solution for at least 2 hours.
  • After the individual loop cleanings, all three were opened up and cleaned as a whole for an additional 8 hours.

RYDLYME results
In less than 24 hours, the entire system was free of deposits prompting our customer to tell us, 'We'll never rod another heat exchanger again!'

Customer comments

No comments were found for We'll never rod another heat exchanger again case study. Be the first to comment!