McCarthy Building Companies to Begin Major Structural Work on Torrance Memorial Medical Center Replacement Tower

0

Source: McCarthy Tetrault

$300 million hospital-wellness facility focuses on patient care with “family-friendly” overnight spaces, healing gardens and chapel

TORRANCE, Calif.--(BUSINESS WIRE)-- McCarthy Building Companies, Inc., one of America’s premier hospital building contractors, is constructing the $300 million Torrance Memorial Medical Center Replacement Tower on the existing medical center site at 3330 Lomita Boulevard. Excavation and shoring for the new construction is nearly complete as the tower’s structural steel is scheduled to begin in October 2011.

“Our partnership with McCarthy in this project will prepare us to offer to our community the most current and effective medical technologies in the most passionate, caring environment possible for decades to come,” said Craig Leach, president and CEO of Torrance Memorial Medical Center. “Once completed, the tower will be unmatched locally in its energy and environmental design efficiencies. It will truly be a beacon for wellness and sustainability.”

McCarthy is the general contractor for the 256-bed replacement project, which began construction in February 2010. The project entails construction of a seven level, 398,350-square-foot patient tower as well as a basement to house a central utility plant and a tunnel connecting the existing hospital to the new facility. Twelve new elevator systems and two exit stairs will be installed, and a 2,770-square-foot Emergency Generator building along with underground fuel oil storage tanks will be constructed on site. Before construction could begin, McCarthy re-routed existing underground utilities servicing the tower around the new tower’s footprint. A new entrance to the existing facility was also built to allow for patient access from a new direction while the tower is under construction.

Designed by HMC Architects, the state-of-the-art tower will be the new front door of the medical center, and the centerpiece of the campus. Being built with a steel frame atop a mat foundation, the tower’s exterior skin will be a combination of metal panel, precast concrete, plaster, and curtain wall. The combination of skin materials for the tower’s façade not only responds to the correct solar orientation to reduce energy consumption, but it also gives the tower a contemporary and elegant aesthetic.

The new tower represents the future of patient care by increasing, consolidating, and reconfiguring the inpatient, outpatient and acute care functions of the medical center campus to better serve patients and staff. The hospital’s design is focused on patient care as well as the comfort of visiting family members.

The new tower will incorporate significant sustainable features equivalent to the same standards required of a Leadership in Energy & Environmental Design (LEED) silver certified structure. Some of the eco-sensitive design features include: minimizing environmental impacts by incorporating optimal building orientation to reduce solar heat gain; individual temperature controls to reduce energy; white roof to minimize heat gain; low-level perimeter building lighting to reduce light pollution; recycled content and environmentally friendly finishes; as well as the use of water efficient landscaping and a healing garden to reduce the “heat island effect” from excessive use of hardscape. McCarthy will also use sustainable construction methods including recycling approximately 80 percent of construction waste; maintaining proper indoor air quality; and utilizing local labor.

“In order to provide the design team with constructability input efficiencies along with a progressive schedule and budgeting information, McCarthy is using a combination of delivery systems. Design-assist will be incorporated to deliver the Mechanical, Electrical & Plumbing (MEP) systems, structural steel, and framing, while design-build will be used for the exterior skin, elevators and fire protection system,” said Patrick Peterson, McCarthy project director.

The construction team is using Building Information Modeling (BIM) technology including NavisWorks 3-D project modeling for clash detection and coordination to assist with extensive MEP overhead and in-wall coordination, as well as seismic bracing, and exterior skin systems.

“Because of the project’s unique challenges, construction will be multi-phased to alleviate disruption to the existing facility,” said Erik Chessmore, McCarthy project manager. “We will be setting the new tower’s central plant equipment in the basement prior to steel and concrete topping out. Furthermore, due to the hospital’s proximity in an operational urban site with limited access, a detailed logistics plan will be utilized and close coordination with the hospital and subcontractors will be required during erection and build-out of the tower.”

Topping out of the structural steel is slated for February 2012, with project completion by November 2014.

About McCarthy

McCarthy Building Companies, Inc. is the largest American-based healthcare builder in the country. The firm has completed over $2.4 billion in healthcare work in Southern California alone. In addition to Newport Beach, McCarthy has offices in San Diego, Sacramento and San Francisco, Calif.; Phoenix; Las Vegas; Dallas; Houston; St. Louis and Atlanta. McCarthy is 100 percent employee owned.

To download high resolution photographs of this project, click on the following link: http://www.mccarthy.com/ftp-torrance-memorial-medical-center/