Demolition Waste Articles

  • Global Site Decommissioning - Case Study

    Challenge: A global oil and gas company required final decommissioning at a former terminal and blending facility that had been idle for almost a decade. The 2.5 acre site, located in South Africa, required the removal of all above and below ground structures, underground utilities, process equipment, buildings, concrete slabs and foundations. The objective of ...


    By Antea Group - USA

  • TELUS and Green Standards Partner to Responsibly Decommission Office Spaces Across Canada

    Green Standards and TELUS, Canada’s fastest growing telecommunications provider, have worked together since 2012 to decommission office spaces across the country, including spaces in British Columbia, Alberta, Ontario, Quebec and Nova Scotia. The Objective: As part of an ongoing strategy to reduce the ...


    By GLOBE Foundation

  • Footwear to Energy

    In developing countries within South East Asia, ever-depleting landfill space, fast-growing populations and an increasing need for more concrete to build, are just some of the factors that make for a compelling alternative fuel production argument. But to what extent is a lack of waste infrastructure holding such countries back? Is legislation the missing ingredient? Or do global brands need to ...


    By UNTHA Shredding Technology

  • Demolition Noise Monitoring with John F Hunt - Case Study

    Cirrus Environmental has enjoyed a long alliance with John F Hunt Demolition going back over many years, so much so, the company’s Health, Safety & Environmental Department has accumulated almost an historic arsenal of Cirrus equipment that charts the journey of noise monitoring over the years. About John F Hunt Demolition The ...


    By Cirrus Environmental

  • Bolderwood Campus Southampton – Case Study

    Project Highlights Envirochem were responsible for organising all consultant and analytical works relating to the removal of all asbestos containing materials from a busy biomedical sciences facility. Our work and advice ensured that both the university and demolition contractor were able to proceed with their building project within a ...

  • RDF production at Delete Oy with UNTHA shredders

    UNTHA’s complete RDF system strengthens Delete’s waste to energy commitment When environmental services specialist Delete needed a new alternative fuel production system for its site in Tampere, central Finland, the €100million turnover company turned to Austrian-based UNTHA. Now manufacturing more than 20 tonnes of 80mm RDF an hour, ...


    By UNTHA Shredding Technology

  • What is Long Term Noise Monitoring?

    It might sound simple, but long term noise monitoring can mean different things to different people. There is no standard definition for what long term noise monitoring is, but here is a summary that covers the basics. I first presented this presentation at the IOA Eastern Branch meeting and wanted to share my thoughts on what classes as long term noise monitoring. I’ll also discuss ...


    By Cirrus Environmental

  • Case study - PCB Containment - ICA of Jacksonville

    Location: Jacksonville, FL System Applied: JBT 303 Substrate / Area: PCB Containment, 38,000 sq.ft. Date Completed: November 2005 Quality Control: Dudley Primeaux II, Primeaux Associates, LLC Project Description The building was scheduled for demolition, but the existing slab was impacted with PCB. It was ...

  • What are the 4 Different Types of Noise?

    Noise comes in all shapes, sizes and sounds. It’s part of our everyday lives but before you can accurately measure it, you need to know what the different types of noise are. Here’s my advice. Whether it’s the innocent beep, a plane flying overhead or heavy machinery in your workplace, you ...


    By Cirrus Research plc

  • Quality means money in shredding C&D and Industrial waste for RDF production

    A typical challenge in turning Construction and Demolition waste (C&D) and Industrial waste into high grade Refuse-Derived Fuel (RDF) is that elastic and stringy materials wrap around the rotor of the shredder. This causes hours of maintenance downtime weekly and has immediate effect on productivity. When using TANA Shark this has not been an issue for our customer Ekokem-TSJ Yrityspalvelut ...


    By Tana Oy

  • Athlone Cooling Towers Demolition, Cape Town, South Africa Case Study

    The Athlone Cooling Towers in Cape Town, South Africa, were condemned due to structural damage caused by the heavy Cape winds. A decision was taken to demolish the Cooling Towers, despite the technical challenges and potential risk to nearby populations that this posed. In 2011, Knight Piesold was appointed as project manager to assist with the demolition of the Athlone Cooling Towers, by the ...


    By WKC Group

  • Springwood Campus - Case Study

    Project: Springwood Campus Client: Bournemouth Borough Council Completed: December 2013 Floor area: 700m² Duration: 5 months Value: £1,700,000 ...


    By Modulek

  • The Carey Group adds Multi-Functional Waste System to its Business - Case Study

    EMS were delighted to be asked to work with the Carey Group, a leading independently-owned construction company operating across the UK and Ireland. The Carey Group is unique within the construction industry due to their internal specialist demolition, civil engineering, concrete structures, building and environmental business units. Being involved in so many areas, they needed a comprehensive ...

  • Construction debris recycle: assigning the costs to where they belong

    The research reported here developed a management model for construction and demolition waste in a Brazilian municipality with material flow sheet and economical balances. This waste is produced at a rate of 1.7 kg per person per day. The private construction sector is called upon to run and fund the waste movement network through correct fee structures. The heart of the network is a sorting and ...


    By Inderscience Publishers

  • Waste quantification models for estimation of construction and demolition waste generation: a review

    Quantification is crucial for construction and demolition waste management. Accurate estimation can be satisfied by developing waste quantification model that is applicable for regional or nation–wide C&D waste generation. This paper presents a review on quantification models for C&D waste from literatures and how they correlate. Most studies combine the empirical waste assessment data or waste ...


    By Inderscience Publishers

  • Recycling construction materials in a developing country: four case studies

    This study identifies, documents, and assesses the existing levels of awareness and implementation of sustainability practices amongst the different participants in the Lebanese construction industry. The analysis is based on a survey of owners, designers, and contractors supplemented with four case studies illustrating the recycling of construction demolition waste (CDW). The results indicate an ...


    By Inderscience Publishers

  • Commercial Varennes, Québec (Canada)

    Status: Under development Feedstock: Sorted industrial, commercial and institutional waste Planned Product: Cellulosic Ethanol Expected Capacity: 38 million litres/ 10 million gallons per year Enerkem and GreenField Ethanol are planning to build Québec's first full-scale cellulosic ethanol ...


    By Enerkem

  • Iford Rugby Club - Case Study

    Project: Rugby Changing Room Facilities Client: Bournemouth Borough Council Completed: April 2012 Floor area: 208m2 Duration: 3 weeks ...


    By Modulek

  • Crusher Plant For Sale

    Crusher Plant For Sale,Crushing Plant For Sale Small Portable Rock Crusher called portable crusher station is fully adaptable to all crushing needs; it set up a new range of business opportunities for contractors, quarry operators, recycling ...


  • Integrated life cycle management of aggregates quarrying, processing and recycling: definition of a common LCA methodology in the SARMa project

    Most of the environmental knowledge, presently used to understand or design sustainable industrial systems, is derived from an application of life cycle assessment (LCA). The mining/quarrying industry is probably one of the sectors where there has been relatively less use of LCA tools, or where LCA has received less consensus. A key issue is the integration between three interdependent life ...


    By Inderscience Publishers

Need help finding the right suppliers? Try XPRT Sourcing. Let the XPRTs do the work for you