A new helicopter manufacturing facility being constructed on the former demolition site.
Ellis provided specifications for removal of all hazardous materials prior to demolition of eleven buildings at this site. This included asbestos, lead, stored solvents and oils. Ellis also provided contract documents for demolition and re-grading of the site. The project was completed within budgeted costs and one week ahead of schedule.
According to the US Environmental Protection Agency's (USEPA) estimation, asbestos cement (AC) pipe accounts for approximately 15% of the total length of pipe networks for water distribution systems in North America; and just as other pipe materials, the AC mains are deteriorating and are in need of attention/renewal. However, there are concerns surrounding the environmental impact of AC pipe renewal that are leading to confusion among the utility managers. The prevailing apprehensions led to the commission of a...
What’s at Stake?
A carcinogen is any substance that can cause cancer. They are chronic toxins that cause damage after repeated or long-term exposure. For some people, the workplace can be a source of exposure to some carcinogens, such as asbestos, benzene, or formaldehyde.
What’s the Danger?
Benzene is a colorless, flammable liquid with a sweet odor. It is among the 20 most widely used chemicals in the United States. It is used mainly as a starting material in making other chemicals, including...
Global has been contracted by the Genesee County Land Bank Authority (GCLBA) to complete pre-demolition hazardous material and asbestos inspections on blighted structures located in the City of Flint beginning in 2002 and continuing through the present. In March and November 2013, Global was awarded multiple contracts from GCLBA, which utilize MBEG and HHF funding sources to eliminate blight and stabilize communities. GCLBA was awarded $3,713,240.00 from the State of Michigan to demolishblighted structures within...
Project Highlights
We have recently completed the clearances at the Former Wills Tobacco Factory in Bristol.
This work involved a large number of site visits and a total of 5 clearances on sprayed asbestos coating (each area requiring approximately 20 pumps).
Project Description
The work commenced on 18th October and was completed on 4th December.We have recently completed the clearances at the Former Wills Tobacco Factory in Bristol.
This work involved a large number of site visits and a total of 5 clearances...
Project Highlights
Envirochem managed and offered the complete package at the best price to fit the clients time restraints and allowing continued unaffected work within the factory. Envirochem utilised asbestos licensed scaffolders, electricians, ceiling fixers, and asbestos removers. Keeping the continuation of the project and overflow of the trades was a logistical difficulty that we completed smoothly.
Project Description
To remove asbestos over-spray and encapsulate asbestos over-spray to beams. To...
Customer comments