Improve drilling efficiencies in high temperature wells
Mud cooler system
End Client
Oilfield service company
Location
Middle East– Land Rig
Well Type
HPHT
Services
Mud cooler
Installation

OSSO’s team delivered and installed a land rig closed loop mud cooler system on the long reach lateral hole sections, where the temperatures exceeded 330ºF. The mud cooling system maintained the downhole temperature that enabled the MWD to operate safely and within its maximum operating temperatures. Throughout the duration of the project, we monitored and evaluated hourly the readings from both the mud cooler and drilling parameters to ensure the equipment was working to its optimum level at all times. The biproduct of cooling the mud at surface improved the overall working environment for the rig crew (HSE).
Our approach significantly helped our client realise safety, environmental, operational and commercial gains. Improving drilling efficiency by effective mud temperature control enabled the hole sections drilled to be completed in a reduced number of days drilling, which equated to a 40% decrease in round trips per section drilled. Additionally, the cost of tool damage beyond repair (DBR) reduced by 95%*.
- Reduced days drilling NPT per section drilled
- 40% decrease in round trips per section drilled
- 95% reduction in tool DBR
- Improved surface working environment for rig crew
- Increased lifecycle of BOP elastomers and mud pump liners
*Ref figures from SPE-203260-MS paper
