Usak Karma OSB - Case Study
Nov. 5, 2018
Project name
Usak Mixed Organized Industrial Zone Wastewater Treatment Plant
Employer
Usak Mixed Organized Industrial Zone
Head of Entrepreneur Association
Contractor
Enta Muhendislik Antma Taah. San. Ve Tic. Ltd. Sti.
Location of the plant
Usak/TURKEY
Scope of work
Industrial and Domestic Wastewater Treatment Plant
Contract Date
2005
Completion Date
2006
Flowrate of the plant:24.000 mJ/ day
Inlet Pollution Parameters:
Pollution coming from the sulfuric wastewater
- COD: 900- 5.120 (avr.2.850) mg/ L
- SS: 2300 mg/ L
- Oil & Grease: 200 mg/ L
Pollution coming from the chromium wastewater
- COD: 1400 mg/ L
- SS: 800- 1200 mg/ L
- Oil & Grease: 100- 250 mg/ L
Outlet Discharge Values
- COD: 300 mg/ L
- SS: 100 mg/ L
- Oil & Grease: 10 mg/ L
- PH: 6-9
Units of the Plant:
Pretreatments of the Sulfuric and chromium wastewater
Homogenization
Chemical Treatment
- Coagulation Basin
- Flocculation Basin
- Sedimentation Basin
Biological Treatment
- Neutralization Basin
- Aeration Basin
- Sedimentation Basin
Sludge Dewatering
- Beltpress