Electrical Resistance Heating in 90ft Bedrock SequenceEasternPennsylvania - Case Study
Mar. 10, 2021
Courtesy ofTRS Group, Inc.
Remediation Goals: 483 lbs VOC removal or 1,640,000 kWh applied.
Most popular related searches
Site Characteristics
- Treatment volume: 11(100yd:
- Vadose& saturated zone: sand and clay over sandstone bedrock sequence
- Baseline concentrations
- 46,000 [jg/L TCE in water
- 527 mg/kg TCE in soil
Operations
- Treatment adjacent to active manufacturing facility
- Total run time: 91 days
- Industry first: treatment of CVOCs in 90-ft thick bedrock layer
- 1,640,000 kWh applied
Results
- Soil: Removed 399 lb of TCE
- Groundwater: 99.9% concentration reduction